Consulting Services for Technical Issues, Commissioning, and Turbine Performance Testing of Andong (500 kW×2units) and Suwha (500 kW×2units) Small Hydropower Plants
Period: April 2026 – Present
Conducted technical assessment of design, operational issues, and commissioning readiness of hydropower facilities.
Provided technical consulting during turbine-generator commissioning and start-up processes.
Executed and supported turbine performance testing, ensuring compliance with applicable standards.
Technical Consulting Services for Naulong Integrated Water Resources Development Project in Pakistan
Providing consulting services as a mechanical and electrical specialist for the Naulong Project
Consulting period : July 2025- July 2026
Client: WAPDA (Water and Power Development Authority), Pakistan. Project funded by ADB (Asian Development Bank)
Turbine Performance Test
Conducting Turbine Performance Test at the Sinseocheon Small Hydropower Plant
Client : KOMIPO, Testing and Analyzing period : March 2025- June 2025
Capacity of Small Hydropower : 2,586kW, Test Method : Index Method